The Journey With AUS Midfield Taxiways Project will establish new midfield taxiways to preserve airfield connectivity between the runways and a new terminal apron. The project includes constructing new airfield taxiway pavement; aircraft rated bridge structures, service roads, utilities, reconfiguration of the south campus drainage, security improvements and, updates to the airfield lighting and signage systems.

Project Renderings

The following is a construction timeline that represents some of the major milestones of the project. All shown project dates are subject to change.
September 2024
Ceremonial Groundbreaking
Oct '24 - May '25
Enabling Work
June '25 - Apr '27
Taxiway Construction
April 2027
Substantial Completion